The research methodology involved a thorough literature review and framing of research questions. Reports published by various research institutes, interviews, and news articles, as well as technical documents, research articles, policies, agreements with contractors, and tender documents were used for data collection. The identified parameters for LCC were then used to assess three buildings as the proposed case study, which are under CPWD in India. CPWD adopted the GRIHA rating system for internal certification of projects as a sustainability rating system. Construction of public projects in India is guided by the CPWD Works Manual [29], which integrates and facilitates implementation of strategies for energy and resource efficiency in each project. The Energy and Resources Institute (TERI) worked with CPWD to facilitate the integration of energy-efficient building measures, which ensured that energy and resource efficiency is an inherent part of the building construction process at CPWD [30].
For this study, parameters identified for LCC of CPWD projects include the additional cost of active and passive design strategies that contribute to climate change mitigation and adaptation. They include Envelope (wall, roof, and fenestration), Heating Ventilation, and Air Conditioning systems (HVAC), Electrical systems (indoor lighting), Building Management System (BMS), GRIHA registration and certification fee, green building consultant fee and post-occupancy audit fee. The cost analysis of outdoor lighting, renewable energy, site works, water saving measures during construction, water works inside the building, rainwater harvesting, and waste management was excluded.
The study aims to restrict the life cycle cost analysis to the cost of specific parameters that have an additional expenditure while also ensuring reduction in carbon emissions. There are also several good practices followed by CPWD that form a part of the GRIHA framework but cannot be included as incremental costs. Cost of measures that do not have a measurable impact on emissions is also outside the scope of this study.
For example, topsoil preservation is a partly mandatory requirement of GRIHA. It is also a good practice followed by CPWD since before GRIHA was adopted. The section on ‘Earthwork’ of Delhi Schedule of Rates (DSR) provides unit cost of excavation and banking of topsoil; however, measuring the impact of preserving topsoil on climate change is outside the purview of this study. Moreover, the cost of topsoil excavation by CPWD cannot be considered an additional cost incurred by the project.
Similarly, replantation of existing tress on site is a GRIHA requirement that entails additional expenditure. It is not included in the CPWD DSR but impacts alleviation of the urban heat island effect, which in turn has an indirect impact on reduction of cooling loads, thereby avoiding carbon emissions. However, the impact and cost of strategies that contribute to reduction of the urban heat island effect is outside the scope of this study.
Even though renewable energy utilization reduces carbon emissions and is included as a measure for climate change mitigation and adaptation, costs of renewable energy systems have not been included in the calculation of project LCC. This is so because the study focuses on active and passive design strategies for optimizing energy consumption while ensuring occupant comfort. Electricity supply using solar energy does not constitute a design strategy. It also does not facilitate optimization of energy use.
As per the Indian Standard on LCC, the term includes all costs and revenues, including initial costs of development, operation, repair, maintenance, energy consumption, rentals, and insurance, and provides an analysis framework that assists in making decisions between different design and specification options with different cash flows over a period.
As per ISO 15686 [31] (International Organization for Standardization, 2020), LCC can address a period of analysis which covers the entire life cycle, taken as 25 years for this study.
The following costs were used to collate the LCC calculation for green (i.e., 4-Star or 5-Star GRIHA rated) and conventional cases (GRIHA 1-Star building as per CPWD DSR 2007) CPWD projects:
Single costs: These are costs that occur only once during the service life of a building:
Initial investment costs include the acquisition costs, planning and design costs, incremental costs of envelope, systems costs for HVAC, lighting and electrical systems, and costs towards obtaining green building certification. Since all projects are government buildings, acquisition costs, and planning and design costs were not considered for this study. All initial investment costs were incurred at the beginning of the study period.
Capital replacement costs include the replacement costs of lighting and HVAC systems. Capital replacement costs are taken as on base date as single costs. The replacement costs of lighting fixtures were calculated in accordance with the fixtures’ specifications and available data. The number of times the fixtures are replaced over the service life of a building depends on the type of the fixture used by each project. Replacement costs of lighting fixtures calculated as per specifications and
available data. The replacement costs have been calculated for 25 years for each
building.
For HVAC systems, the replacement is assumed to occur every 20 years.
Resale value of building is the remaining value at the end of service life (i.e., 25 years). Residual costs such as resale values, salvage value or disposal value is taken as
single cost. For this study, and as per discussions with financial experts, it was assumed that the residual value for the project was 6% of the initial investment cost, which increases at 8% annually.
Uniform annually recurring costs are costs that occur every year during the service life of the building and occur in the same amount (constant amount) every year. These costs include the following:
- Operating cost, maintenance cost, and repair costs were considered at 5% and 10% of system cost for green and conventional CPWD buildings, respectively. These figures were also validated as per the annual O&M agreements of case study buildings between CPWD and service providers.
Nonuniform annually recurring costs are costs that occur every year but tend to increase at a constant escalation rate every year over the service life of the building. They include the following:
- Energy cost of building due to lighting, HVAC equipment and electrical systems. Usually, energy consumed in a building comprises electricity, diesel, liquefied petroleum gas and other costs. However, for the purpose of this study, only electricity consumption was considered because the maximum energy usage by a building is in the form of electricity. Annual energy consumption figures for conventional buildings were calculated based on energy simulation reports. These figures were then multiplied by the unit electricity tariff to obtain the annual energy costs for conventional cases.
There are several tools to measure the financial performance of any investment. Key decision-making parameters that emerge from LCC studies include life cycle cost, payback period, net savings (NS), savings-to-investment ratio (SIR) (adjusted), internal rate of return (IRR) and annual cost (AC) or annual equivalent value (AEV).
Life Cycle Cost: Single net present value (NPV) in monetary terms is useful in the economic evaluation of alternatives for building design and specification. Currently, decisions on the construction of commercial, institutional, and residential buildings are based on initial costs or capital investment values, which might be misleading. Once the present costs of the project have been determined, the values are summed up to assess the total life cycle costs for the green and conventional cases of the building. A low LCC indicates a cost-effective project. Equation 1 presents the different parameters used in LCC calculations.
LCC = PVI + CRC + EC + OMR – RV, (1)
where LCC is the total life cycle cost of building in current value; PVI is the present value of investment costs; CRC is the present value of capital replacement costs; EC denotes the present value of energy costs; OMR represents the present value of non-fuel operating, maintenance, and repair costs; and RV is the present value of resale.
Payback Period is defined as the time taken to cover the investment costs through cumulative savings during operation of the building. The project is considered cost effective if the discounted payback period DPP) is less than the study period.
where t is the payback period taken in the framework equal to 25 years, and all the costs in Equation 2 represent the difference between the costs at years 1 and 25.
Net savings (NS), expressed in terms of the present value (i.e., discounted) of the unit of currency, is the difference between operations-related savings and the additional investment costs. Choosing an alternative with the highest NS is the same as the one with the lowest LCC.
Savings-to-investment Ratio (SIR) is calculated by dividing the future (net) savings by the increased investment costs. It is generally expressed in present value (i.e., discounted). An SIR greater than one indicates that the alternative is cost effective. Multiple projects can be prioritized using SIR by ranking their SIRs in descending order and choosing the projects with the highest SIRs. The costs given in Equation 3 are the costs used for calculating SIR.
where ΔI is called the initial incremental investment and is calculated by subtracting the initial investment in the conventional (non-green) building case from that in the green building case.
Adjusted Internal Rate of Return (AIRR) is the compound rate of interest, which when used to discount the cost and benefits over the period of analysis would make costs equal to benefits when cash flows are reinvested at a specified interest rate. By using AIRR, the discount rate that would generate a zero NPV can be calculated.
Annual Cost (AC) or Annual Equivalent Value (AEV) is a uniform annual amount equivalent to the project net costs, considering the time value of money throughout the period of analysis. The alternative with the lowest AEV would also have the lowest total cost.
Projects may use LCC to estimate the overall costs of project alternatives and select the design that ensures that the facility will provide the lowest overall cost of ownership consistent with its quality and function. In this study, single net present values for life cycle costs were calculated. The payback period and SIR were also calculated.
2.1 Data Collection
The approach adopted for data collection based on parameters identified for the LCC analysis of the selected CPWD project was as follows. A review of primary documents (for construction and operation) including the final agreement between CPWD and contractor, final bill under CPWD agreement and tendered BOQ from CPWD was conducted. Then, a questionnaire for green building consultants was prepared, in which interviews and discussions with concerned CPWD officials were conducted. A conventional base case (as per CPWD Plinth Area Rates and Delhi Schedule of Rates) for the case study was created to be used in the comparison between the green building and conventional alternatives.
Three buildings were used as case studies: Indira Paryavaran Bhawan, Jor Bagh, New Delhi; Lecture Theatre and Lab Complex at IIT Delhi; and Punjab National Bank Corporate Headquarter, Dwarka, New Delhi (hereinafter referred to as IPB, IIT, and PNB, respectively). Case study selection in terms of data availability and collection for this research was covered under the ambit of the Memorandum of Understanding (MoU) signed between SPA Delhi and CPWD on 29th April 2019 (Annexure 1). Since GRIHA was endorsed by CPWD in 2009, it was decided by SPA Delhi and CPWD to identify and study buildings constructed by CPWD in Delhi NCR (composite climate zone) between 2009 and 2019. Selection of case study buildings is based on the following parameters:
• To be minimum 4- or 5-Star GRIHA rated (or provisionally rated) and comply
with relevant and applicable Indian codes and standards in a composite climate
zone.
• Building use to be institutional and project to be operational (day use).
• 40% (or more) of the building to be air conditioned.
• Built-up area to be more than 20,000 m2 (i.e., project eligible for seeking
environmental clearance).
Tables 1 and 2 give the details of these buildings.
TABLE 1. Key information about the case studies
|
Building
|
Built-up Area
|
Total Project Cost (Rs.)
|
Date
|
Salient Features
|
Indira Paryavaran Bhawan
|
31,400 m2
|
Rs.199.88 cr (Rs.63,670/m2)
- Civil: 63.45 cr (31.74%)
- Electrical: 23.51 cr (11.76%)
|
2014
|
- GRIHA 5 Star (provisional)
- Optimal North–South orientation
- WWR = 17%
- Daylight integration
- Self-shading
- EPI: 39.29 kWh/m2/annum
- 930-kWp rooftop solar power plant
- Chilled beams for air conditioning
- Geothermal heat exchange system
- LED fixtures+ sensors
- Robotic car parking in basements
- Energy saving regenerative lifts
- Pervious paving
- Fly ash-based construction material
|
Lecture Theatre and Lab Complex at IIT Delhi
|
45,761 m2
|
Rs.115 cr
(Rs. 25,130/m2)
- Civil: 100.6 cr (87.47%)
- Electrical.: 3.35 cr (291%)
|
2015
|
- GRIHA 4 Star (provisional)
- North–South orientation
- WWR = 23.5%
- Daylight integration
- Strong shading strategy
- EPI: 59.06 kWh/m2/annum
- 5-MWp solar system on campus
- CFL and T5 fixtures
- Fly ash-based material
|
Punjab National Bank Head Office
|
76,188 m2
|
Rs.405 cr
(Rs. 53,160/m2)
- Civil: 137 cr (33.82%)
- Electrical: 66 cr (16.29%)
|
2017
|
- GRIHA 5 Star (provisional)
- WWR = 35.4%
- Daylight integration
- EPI: 43.5kWhr/m2/annum
- 202KWp rooftop solar PV
- LED fixtures+ sensors
- Pervious paving
- Fly ash-based material
|
A summary of building envelope specifications of the three case study buildings is provided in Table 2. Further, a summary of the building energy systems in the three case study buildings is provided in Table 3.
TABLE 2. Case study building envelope specifications.
Building
|
Climate zone
|
Building materials (envelope)
|
Wall
|
Glazing
|
Roof
|
IPB
|
Composite
|
• 200-mm AAC Block + 50-mm rockwool + FaLG bricks • U-value 0.37 W/m2K
|
• U-value of external window assembly: 1.5 W/m2K • VLT: 0.59 • SHGC: 0.31
|
• Brick koba treatment + PUF + heat reflective tiles • U value of roof assembly: 0.26 W/m2K
|
IIT
|
Composite
|
• 200-mm AAC Block + 30-mm rockwool + 100-mm AAC Block • U-value 0.39 W/m2K
|
• U-value of external window assembly: 1.48 W/m2K • VLT: 0.49 • SHGC: 0.22
|
• RCC slab + 75-mm XPS + tiles • U value of roof assembly: 0.31 W/m2K
|
PNB
|
Composite
|
• Thick stone cladding + 230-mm fly ash brick + 115-mm fly ash brick + Plaster • U-value: 0.766 W/m2K
|
• U-value of glazing for air-conditioned area: 1.9 W/m2 °K • VLT: 0.39 • SHGC: 0.28
|
• RCC slab+50-mm fiber glasswool + 150-mm brick coba • U value of roof assembly: 0.596 W/m2K
|
TABLE 3. Case study building energy system details.
|
|
Building energy systems
|
Building
|
Lighting
|
HVAC
|
Electrical system
|
IPB
|
• Daylight integration (75% occupied areas daylit) • T5 lamps with electronic ballasts • LEDs • Daylight/lux level sensors • Occupancy/motion sensors • LPD: Better than ECBC requirement •10% of total energy demand
|
• Room temperature of 26 ± 1°C • 64% superstructure air conditioned • Cooling load: 400TR 1. 2×240 TR water cooled screw chillers (1 working+1 standby) 2. 160TR Geo Thermal system with chilled beam system 3. 200 TR water screw chiller for chilled beam system. •35% of total energy demand
|
• Total load: 830 kW • Transformers: 2×1000-kVA dry type + 1×1250-kVA step-up to supply from solar grid to NDMC • DG sets: 2×500-kVA radiator cooled • UPS • Integrated building management system
|
IIT
|
• Daylight integration (76.6% occupied areas daylit) • LEDs • Daylight/lux level sensors • Occupancy/motion sensors • LPD: Better than ECBC requirement •7% of total energy demand
|
• Room temperature of 26 ± 1°C • 69% superstructure air conditioned • Cooling load: 660TR 1.3×375 TR water cooled chillers (2 working + 1 standby) •84% of total energy demand
|
• Total load: 2195 kW • Transformers: 3×1000-kVA dry type • DG sets: 4 (2×1000-kVA gas based + 1×500-kVA diesel based + 1×380-kVA diesel based) • UPS • Integrated building management system
|
PNB
|
• Daylight integration (51.6%occupied areas daylit) • T5 lamps with electronic ballasts • CFLs • LPD: Better than ECBC requirement •25% of total energy demand
|
• Room temperature of 24 ± 1°C • 40% superstructure air conditioned • Cooling load: 550TR 1. 3×275 TR variable air volume with water loop chiller system (2 working + 1 standby) •16% of total energy demand
|
• Total load: 1271 kW • Transformer: 1000 kVA + 3×2000 kVA • DG sets: 500 kVA + 750 kVA •UPS: 100 kVA • Integrated building management system
|
2.2 Statistical Data Analysis
Statistical analysis was performed using SPSS version 21.0 for Windows, (SPSS, Chicago, Illinois). Continuous variables were presented as mean ± standard deviation (SD) and median as interquartile range (IQR). Data were checked for normality before statistical analysis. Non-normally distributed continuous variables, namely Single Investment Cost, Capital Replacement Cost, Energy Cost, Recurring Cost and Cumulative Cost, were compared using the Mann–Whitney U test between IPB, IIT, PNB and the corresponding conventional buildings. For the statistical test, a p-value less than 0.05 was taken to indicate a significant difference.